Opel Vectra B

since 1995 release

Repair and operation of the car



Vektr's Opel of B
+ 1.1. Governing bodies and control devices
+ 2. Maintenance
+ 3. Engines
+ 4. Heating, ventilation
+ 5. Fuel system
+ 6. Systems of start, ignition
- 7. Transmission
   + 7.1. Coupling
   + 7.2. Mechanical transmission
   - 7.3. Automatic transmission
      7.3.1. Introduction
      7.3.2. Technical characteristics
      7.3.3. Replacement of oil in the transmission
      7.3.4. Adjustment of the lever of the selector
      7.3.5. Selector cable
      7.3.6. Selector lever
      7.3.7. Replacement of a sealing ring of the hydrotransformer
      7.3.8. Electric elements of control of the transmission
      7.3.9. Switch of a manner of the movement
      7.3.10. Electronic control device
      7.3.11. Sensors of the entrance and conducted transmission shaft
      7.3.12. Transmission oil temperature sensor
      7.3.13. Removal and installation of the transmission
      7.3.14. Capital repairs of the transmission
   + 7.4. Power shafts
+ 8. Brake system
+ 9. Running gear
+ 10. Body
+ 11. Electric equipment
+ 12. Main malfunctions


d65d3f49

7.3.4. Adjustment of the lever of the selector

GENERAL INFORMATION

Prevention

If shutdown of the accumulator is made with the selector lever in situation P, the lever will be fixed in this situation.


PERFORMANCE ORDER
1. For release of the lever from fixing remove finishing of the lever of the selector and, using an edge of the thin screw-driver, press the clamp lever on the left forward side of the lever of the selector.
2. Move the selector lever to all provisions and check that the included transfer correctly is displayed on the indicator of position of the lever of the selector.
3. Install the selector lever in situation P.
4. For access to a cable of the choice of transfers remove the accumulator and a support of the accumulator.
5. Take a bracket of blocking and release a cover of a cable of the choice of transfers from an arm on the top part of the transmission.
6. Check that the lever of the selector (1) is installed in situation P (2), then move the lever to all provisions and establish it in a starting position. Record a selector cable cover pressing of a bracket of blocking before click.
7. Install the accumulator and check operation of the lever of the selector.